Establishment of store and its planning 

Whenever we keep some materials with record systematically in a particular  place and using  the same as per daily requirement we require some planning in a proper manner is called store keeping with the usage capacity either in sq. meter/tonnage/cum/Kilo liter etc.

Therefore if you would like to construct stores in a hydro sector of different sizes according to use like spare parts, steel, oil, cement, assorted miscellaneous materials etc you may write to us info@hpcs.co.in we will provide detail planning with illustration to you. Initially we may arrange a demo at your site in power point if it is desired. Please note that we do not provide foundation drawings.

 

Equipment planning for medium size tunnel 

For construction of head race tunnel usage of equipment various as per geological conditions for example in class-1 & class-2 rocks types of equipment changes with class-3 & Class-4 types of rock   i.e. medium to hard type and decomposed to soft type of rock otherwise your progress rate will be slow therefore we are confused what type of equipment should be used when you can not predict what type of rock is coming across.

Therefore you may be required to change excavation equipment after 50% excavation works in the middle way which will be a matter of investments a huge amount or delay in construction of head race tunnel. We may provide a correct decision so that you need not to be changed equipment all of a sudden. Our expert team will provide correct planning as per rock conditions and with detail illustration. Therefore incase of any abnormal situation please Contact to our mail address info@hpcs.co.in

 

Maintenance of Plant & equipment & Cost of repair 

It is a well-known fact that our daily progress suffered mostly due to breakdown of equipment, as such maintenance of plant & equipment and allocation of fund for R&M is most important because if you do not perform the normal periodic maintenance of equipment the cost of repair shall be higher than the normal cost. It has been seen in a hydro sector private developers do not keep stand by equipment or they use stand by equipment only incase of break down as a support to run the work.

If you are finding such type of difficulties to run the equipment in a systematic manner our extensive package will help you and reduce the repair cost drastically whatever R&M team you are having or not. You may contact us to our mail address info@hpcs.co.in for corrective procedure. We may arrange a demo in power point if it is desired so.

 

Ventilation system for head race tunnel  

The ventilation of under ground works is important when the length of tunnel is more than 500 M. However ventilation of any types of tunnels either it is HRT, TRT, desilting chamber, under ground power house etc ventilation system is must from the beginning of portal establishment. To calculate the blower HP and air required at face the fowling parameter must be known:-

1.      No of Diesel equipment and other equipment working inside the tunnel.

2.       No of persons are working inside the tunnel.

3.       Area of the tunnel.

4.       Cross section of ventilation duct.

You may contact to our web site info@hpcs.co.in for further details. We may arrange a demo in power point if it is desired.